Bathroom Renovation Cost Calculator
Estimates the cost of a bathroom renovation in Ireland from floor area, works type, finish quality and whether sanitaryware and taps are replaced.
In a 5 m² bathroom with a mid-range renovation (all tiles replaced and new sanitaryware), the works cover about 23 m² of surface: roughly 5 m² of floor and 18 m² of wall tiling up to 2.20 m high. The job also involves three sanitary fittings: a toilet, a basin and a shower tray.
The works type changes the scope more than any other factor. A cosmetic refresh leaves the tiles and sanitaryware alone, so the work is limited to painting with a paint suited to humid rooms, replacing accessories and, if wanted, a new tap or toilet. A mid-range renovation strips out the existing tiles, adds a waterproofing layer on walls and floor, and fits new tiles and fittings. A full renovation goes further and moves the drainage or water supply to a new position, which enlarges the area that has to be opened up and rebuilt.
Finish quality is the second variable. Tile, sanitaryware and tap choices differ widely in both price and fitting difficulty. Large-format porcelain tiles, for example, need a flatter substrate and more skilled fixing than standard ceramic, so the labour cost per square metre can rise even when the tile itself is not dramatically more expensive.
Enter the bathroom floor area, then select the works type, the finish quality and whether the toilet, basin, shower tray or bath and the taps are being replaced. The calculator shows the estimated total cost by component, so you can see where the budget goes and test how each choice changes the total before you ask contractors for quotes.
The result updates automatically.
Small toilet: 2–4 m² (about 22–43 sq ft). Full bathroom: 4–10 m² (about 43–108 sq ft).
Base cost per square metre, sanitaryware prices and tap prices are not stated here because they vary between suppliers and over time. Enter the figures from your own written quotes to refine the estimate. Quoted labour rates differ between contractors, so local written quotes are the best reference. Technical requirements for bathrooms come from the Irish Building Regulations (Technical Guidance Documents C, F and G) and the national wiring rules.
Toilet, basin and shower tray or bath.
Basin tap and shower or bath mixer.
Estimated cost
Mid-range · Mid-range · 5.0 m²
- Building work and base materials
- €3,000
- Sanitaryware
- €1,100
- Taps and mixers
- €425
- Cost per unit of area (estimate)
- €905/m²
How it works
Formula
How the calculation works
Bathroom renovation costs: what drives the budget
Renovating a bathroom is one of the jobs most likely to exceed its original budget. The main reason is what sits behind the tiles: old supply pipes, cracked plaster, damp that has been hidden for years and drainage runs that do not match any plan. Many Irish homes, particularly older houses and period properties, have bathrooms fitted decades ago that were never designed for today's sanitaryware or tile sizes. Unexpected repairs are common enough that they should be planned for, not treated as a rare event.
The works type defines the scope
The works type has the largest effect on the total cost.
A cosmetic refresh leaves the tiles, sanitaryware and drainage untouched. The work focuses on visual change: repainting the walls with a paint suited to humid rooms, replacing accessories such as the towel rail, toilet roll holder, mirror and light fittings, and fitting a new tap. A new toilet is sometimes added. This is the least costly option and suits bathrooms that are relatively recent but look tired.
A mid-range renovation is the most common choice when people say they are “doing up the bathroom”. It includes removing all existing tiles, installing a new waterproofing layer on walls and floor, fitting new tiles, and replacing the toilet, basin, shower tray or bath and the taps. The waterproofing matters because it stops water reaching the structure and the floor below. Technical Guidance Document C, which supports Part C of the Building Regulations on resistance to moisture, expects walls and floors exposed to water to resist moisture penetration. Tanking the surfaces behind the tiles before tiling is standard practice in wet areas, and the cost of doing it properly should be in the budget from the start.
A full renovation covers everything in the mid-range scope and adds structural or service changes. Typical examples are moving the toilet, basin or shower to another position, which means relocating waste pipes and the hot water supply, changing the extract ventilation (Technical Guidance Document F covers ventilation), or altering the electrical circuit to add a shower, extractor fan or electric heater. Partial removal of a wall may also be needed. This is the most expensive option. The cost before sanitaryware and taps is considerably higher than for a mid-range renovation of the same room.
Floor area matters less than expected
Cost does not scale directly with floor area. The largest single element is labour to install the sanitaryware and services, and a plumber spends roughly the same time connecting a toilet in a small room as in a slightly larger one. Area does drive tile and material costs, which is why the calculator applies a base cost per square metre to the floor area.
In a 5 m² room, the wall area to be tiled up to 2.20 m high is in the region of 15 to 18 m², depending on the shape of the room, the door and window openings, and the tile height chosen. That wall area is where most of the tile quantity comes from, so a room with more openings or a higher tiled height will cost more than the floor area alone suggests.
Material and labour cost per square metre also varies with the tile. Standard ceramic wall tiles in the budget range are easier to fit and cheaper than rectified large-format porcelain, such as panels of 60 × 120 cm. Large tiles need a flatter substrate, more skilled fixing and more careful handling, so they can raise the cost noticeably for the same area.
Finish tiers and labour
Sanitaryware varies widely between tiers. Budget ranges typically use a standard acrylic shower tray and a simple toilet and basin set. Mid-range ranges are the most common choice in standard renovations. Premium pieces may include a wall-hung basin, a concealed cistern, a glass shower screen or a concealed shower valve. The calculator asks for a finish tier rather than a product name, because product lines change often and a named product quickly becomes outdated.
Quoted labour rates differ between contractors, and a contractor's availability can affect the timetable as much as the price. Written local quotes are therefore the best reference for the labour element of the base cost.
Items that are often forgotten
Several items are small individually but add up quickly when they are left out of the budget:
- Waterproofing, and the curing time it needs before tiling, as set out in the product's technical data sheet. Tiling too early can cause failures that appear months later.
- Trim and transition profiles between the bathroom floor and the hallway floor.
- Sealant in movement joints, at the junction between wall and floor, at internal corners, and around the basin, bath and shower tray.
- Extract ventilation, which controls humidity in the room and should be budgeted rather than assumed to be in place.
- Final decoration, including paint, and the snag list at the end of the job.
When to bring in a professional
For cosmetic work that does not touch pipes or wiring, a competent painter or general builder is enough. Mid-range and full renovations that involve plumbing, drainage or electrical work need a qualified plumber and a registered electrical contractor. Electrical work in a bathroom must follow the zoning rules in the national wiring rules (I.S. 10101) and the Part P requirements, and it should be certified on completion.
Whether planning permission is needed depends on the works. Internal alterations that leave the external appearance of the building unchanged are generally exempt development under the Planning and Development Regulations 2001 (as amended), but the local authority should be checked before work starts.
Work that alters structural walls, moves drainage or changes the layout may fall under the Building Control Regulations and require a commencement notice to the local authority. Where a design is needed, a qualified architect or chartered engineer should prepare or sign off the drawings. In multi-unit developments, works affecting common pipes or common parts need the consent of the owners' management company under the Multi-Unit Developments Act 2011.
Before hiring, check that the contractor holds a current Revenue tax clearance certificate and has public liability insurance, and ask for written quotes that list the scope item by item. Quotes that differ widely usually differ in scope, not only in price.
How the formula works
The calculator estimates the total cost with the expression C = A × b + L + T.
A is the bathroom floor area, measured inside from wall to wall. The base cost is applied to the floor area, so the estimate assumes a room of typical proportions. A very tall, very narrow or heavily broken-up room will differ from the estimate, and a surveyor's measurements are more reliable than an approximate figure.
b is the base cost per square metre of floor area. It covers the labour for strip-out, waterproofing, tiling and installation, together with the building materials. Its value is set by the works type and the finish quality you select.
L is the cost of the sanitaryware. It is zero when the existing toilet, basin, shower tray or bath stays in place.
T is the cost of the taps and mixers. It is zero when the existing taps stay in place.
If both the sanitaryware and the taps are kept, L and T are zero and the estimate reduces to A × b. A zero floor area gives a result equal to L + T alone, which has no practical meaning for a bathroom and should not be used. Negative values are not valid inputs.
Common mistakes
The most common error is entering the wall area instead of the floor area. The second is leaving the sanitaryware option switched on when the existing toilet and basin are staying, which overstates the estimate. The third is treating the result as a quote. The calculator cannot see the condition of the pipes, the state of the floor screed or the damp behind the plaster, and those unknowns are where most overruns start.
When not to use the calculator
Do not use the result as a budget for a structural project, a commercial bathroom, a wet room with a large custom tray, or a renovation that changes a shared building element. In these cases the estimate is only a starting point. A surveyor, architect or engineer should prepare the scope, and the budget should be built from itemised quotes.
Frequently asked questions
What determines the cost of renovating a bathroom in Ireland?
The works type and the floor area matter most. A cosmetic refresh is the least costly option. A mid-range renovation with new tiles, a waterproofing layer, sanitaryware and taps costs substantially more, and a full renovation that moves drainage or the water supply is the most expensive. Area matters less than many people expect, because a plumber spends roughly the same time connecting a toilet in a small room as in a larger one. Enter your own measurements and choices in the calculator to get an estimate for your scenario, then compare it with written quotes from contractors.
What does a full bathroom renovation include?
A full renovation typically includes stripping out the existing tiles and floor finish, a waterproofing layer behind the tiles and under the floor finish in wet areas, plastering or skimming of walls where needed, new tiling, installation of the toilet, basin, shower tray or bath and the taps, plumbing and electrical work (including extract ventilation and any shower or heated towel rail circuit), and final sealing around the basin, bath and shower tray, painting and the snag list. If drainage or the water supply is moved, the scope also includes opening the floor and rebuilding the affected pipework.
How long does a bathroom renovation take?
A cosmetic refresh usually takes a few days, mostly for painting and fitting accessories. A mid-range renovation takes considerably longer, because stripping out, waterproofing, tiling and fitting of sanitaryware follow each other in sequence, and each stage has to cure or set before the next can begin. A full renovation with pipework changes can take several weeks. Timings depend on the availability of tradespeople and on any surprises found behind the existing tiles, so agree a schedule and a snag list before work starts.
Is planning permission needed to renovate a bathroom?
Planning permission is generally not needed for internal bathroom works that leave the external appearance of the building unchanged, because such works are usually exempt development under the Planning and Development Regulations 2001 (as amended). Works that alter structural walls, change the layout of drainage or affect a shared building element may need a commencement notice under the Building Control Regulations. A flat in a multi-unit development may also need the owners' management company's consent under the Multi-Unit Developments Act 2011 if the works affect common parts. The exemption depends on the specific works and the property, so check with your local authority before you start.
Which sanitaryware and taps offer good value?
The calculator asks for a finish tier rather than a brand, because product lines change often and brand names date quickly. Budget sanitaryware usually has a standard acrylic shower tray and a simple toilet and basin set. Mid-range lines are the most common choice in standard renovations. Premium pieces may include a wall-hung basin, a concealed cistern or a glass shower screen. Compare the technical data sheets of the products you are considering, check the warranty terms, and confirm that the fittings suit your existing pipework and drainage positions.
Do I need a registered professional for a bathroom renovation?
For cosmetic work that does not touch pipes or wiring, a competent painter or general builder is enough. For mid-range and full renovations that involve plumbing, drainage or electrical work, use a qualified plumber and a registered electrical contractor, and check that every contractor you hire holds a current Revenue tax clearance certificate. Electrical work in a bathroom must follow the zoning rules in I.S. 10101 and the Part P requirements, and it should be certified on completion. For work that changes the structure or the drainage, a design prepared or signed off by a qualified architect or chartered engineer is strongly recommended.
Related calculators
View all Renovation & Systems calculators →
By RivoCalc · Reviewed under our editorial methodology · Updated 3 June 2026
This calculator gives an estimate for planning purposes only. Real costs depend on the condition of the existing bathroom, the contractor, local labour rates, the materials chosen and any hidden defects found once work starts. Obtain written quotes before committing to a budget.